During the construction phase
the contractual arrangements should be that the contractors responsible
for commissioning shall submit information about the equipment
installed, method statements for testing, arrangements for training, etc.
LEED-NC
The CxA
shall review contactor submittals applicable to systems being
commissioned for compliance with the OPR and BOD. This review shall be
concurrent with AlE reviews and submitted to the design team and the
Owner. The CxA shall provide a review of the contractor submittals to
help identify any issues that might otherwise result in re-work and/or
change orders. The CxA should specifically evaluate the submittals for:
# Meeting the OPR and BOD
# Operation and maintenance requirements # Facilitating performance testing
The CxA review of contractor submittals does not, typically, substitute or alter the scope or responsibility of the design team's obligations to approve or reject submittals.
|