Building
life-cycle performance depends on the quality of process from planning
through to demolition, including testing and commissioning. The costs
for commissioning depend on the scope of work and quality of management
oversight, with the benefits also dependent on the persistence of the
commissioning outcomes.


Scope
of New Building Commissioning
World-wide
the scope and depth of building commissioning varies, from minimal or
no testing to full building commissioning embracing all phases of a
project. Essentially the scope of commissioning activity can be
summarised as illustrate in the following illustration [1].

Testing & Commissioning
In
Hong Kong Testing and
Commissioning (T&C) is generally regarded as testing of
equipment and systems separately, generally towards the end of the
construction phase, as illustrated in the figure above.
The
outcomes from Hong Kong’s
T&C practice are often unsatisfactory, especially HVAC systems
[2]. Whilst ArchD’s T&C specifications and
instructions are comprehensive, the extent to which systems will be
fully commissioned will depend on the skill and diligence of the
various sub-contractors employed, and the engineers and inspectors who
vet the outcomes. Even if T&C for each system is complete, and
there is much evidence to suggest otherwise, it is unlikely that
conflicts between systems will be fully resolved. The private sector,
whilst adopting Government T&C specifications, is perhaps under
less due diligence with respect to quality assurance, so it seems that
there is even less likelihood that T&C will be fully implemented
[1].
Completion
of fire services installations (FSI) is prerequisite to obtaining an
occupation permit for a building, with potentially significant economic
losses if delayed. According to a survey by Fong et al [3] the
principal factors contributed to construction delays were: improper
site co-ordination and management of the electrical and mechanical
installations, lack of timely decision making by the client, and
defects identified during the fire services inspection by local
authorities. The factors contributing to the delays included inadequate
site management and supervision, workload of the project staff,
procedures for equipment approval, and working experience of the
parties involved.
According
to McMahon T&C of Hong Kong’s
ultra-modern buildings is routinely undertaken by inexperienced,
unqualified technicians. T&C is viewed as a low-class activity,
which is largely carried out by contractors for contractors, with
problems routinely undetected or deliberately concealed. The potential
for long-term substandard performance and energy wastage as a result of
poor T&C are obvious, yet the practice as a whole never receives
the status and importance that it deserves. McMahon’s observation
is that project managers rarely approach commissioning in a thorough,
co-ordinated manner and instead of being considered and addressed at
the design and installation phases, T&C is routinely
“squeezed into the latter stages of a project when it is often
too late to address the problems that come to light”.

“Much
of the construction process is heavily reliant on the skill and
knowledge of site personnel …. Adequate site supervision is,
therefore, crucial to ensure the delivery of works to
specifications…. Otherwise, costly rectification and programme
delays would result.”
“it
is crucial to ensure that adequate supervisory provision (especially at
professional level) is made for critical stages of
construction...” (4.34)
“Independent
auditing provides checks and balances to guard against unsatisfactory
work...”
Commissioning
Management
In the
UK Commissioning Management places
emphasis on a more integrated approach to the commissioning of building
services systems, i.e. the advancement of installations from static
completion to full working order, including the regulation and fine
tuning of systems [4], and is now a requirement of the UK
building regulationscovering the energy performance of non-domestic buildings.
Until
recently, commissioning practice in the UK also tended to be
fragmented and undertaken towards the end of construction. According to
CIBSE [4], “the commissioning programmes produced by building
services installers and their sub-contractors are frequently
over-optimistic and uncoordinated. They assume that others will
co-operate in providing water, gas and electric supplies, a
weather-tight building, unobstructed access and a dust-free
environment. A risk of project overrun will exist unless the
interdependencies of all the building services systems and plant are
identified, together with their integration with on-going construction
activities. This complex, and highly fragmented part of the
construction process demands good management”.
Commissioning
Process
ASHRAE’s
guideline [5] details the process, responsibilities of the
commissioning team, role of the Commissioning Agent, and a model
framework for developing a Commissioning Plan, specifications and
reports, together with general requirements for operator training and
documentation. The guideline makes reference to other technical
guidelines for specific commissioning information for the building
systems.
The US
General Services Administration’s (GSA) guide details the commissioning team members,
commissioning activities and responsibilities for each phase of a
project, from pre-design through to handover and early stages of
occupancy and operations (figure below). The Commissioning Agent is one
having the technical background and expertise with the commissioning
process including verification techniques, functional performance
testing, system and equipment, and O&M knowledge in order to
successfully manage the process on behalf of the client.
The
Commissioning Process as envisaged by GSA and ASHRAE is not seen as an
additional layer of construction or project management, rather its
purpose is to reduce the cost of delivering construction projects and
increase value to owners, occupants, and users. It assumes that owners,
designers, contractors, and operations and maintenance entities are
fully accountable for the quality of their work, but seeks to provide
for better co-ordination of commissioning activities. Emphasis is
placed on documentation of the Client’s requirements at an early
stage of a project, and the proper transfer of information between all
parties involved in design, construction and commissioning.

Commissioning Existing Buildings
Re-Commissioning occurs when a building that has already been
commissioned undergoes further commissioning. The decision to
recommission may be triggered by a change in building use or ownership,
or because of operational problems. A plan for recommissioning should
be established as part of the original commissioning process for a new
building, or for the retrocommissioning process for an existing
building (Commissioning Collaborative Cx Guide).

Retro-commissioning is a process that intends to improve how building systems function together. Retrocommissioning can often resolve problems that have occurred during design or construction, or address problems that have developed throughout the building’s life. It improves a building’s operations and maintenance (O&M) practices to enhance overall building performance.
Building
Commissioning Association (BCA) regards Existing
Building Commissioning as a systematic process for investigating,
analysing, and optimising the performance of building systems through
the identification and implementation of low/no cost and capital
intensive facility Improvement measures and ensuring their continued
performance over time. The Existing Building Commissioning process
assists in making the building systems perform interactively to meet
the current facility requirements.
[1] Burnett J. Costs and Benefits of Building Commissioning. Trans. HKIE Vol. 15. No. 2. (2008).
[2] Lau, K.F., Chan, Y. C., An Overview of Testing and Commissioning of HVAC Systems in Hong Kong. Proc. ASHRAE/CIBSE/HKIE Joint Symposium. Hong Kong (2002).
[3] Fong, N.K., Wong, L.Y., Wong, L.T. Fire services installation related contributors of construction delays. Building and Environment. Volume 41, pp211-222. (2006)
[4] The Chartered Institution of Building Services Engineers. Commissioning management. CIBSE Commissioning Code M. (2003)
[5] ASHRAE Guideline 0-2005 The Commissioning Process (2005).